Fixing lap cladding
| Shiplap up to 150mm |
Shiplap over 150mm |
Halflap up to 150mm |
Halflap over 150mm |
Includes – Shiplap, Half lap
Horizontal attachment
Begin at the bottom, ensuring that the first board is level with the lap that is adjacent to the wall, pointing upwards. For boards up to 150mm wide, use a single fixing located 25 – 30mm above the lower lap. Never nail through the lap joint. For boards over 150mm, use two fixings, with the second located a further 65 – 75mm above the first to allow for some dimensional movement.
Leave a gap of approximately 2mm between each of the subsequent boards to allow for possible expansion.
Vertical attachment
Start at one corner, with the lap that is adjacent to the wall, facing away. Nail as with the horizontal attachment.
Other Fixing advice available
|
|









Back to Fixing Advice